PM Toolkit ▸ Team Analytics DEMO Team Atlas · Sprints 40–46 · updated daily from Jira

Numbers that change the next planning.

Not vanity charts — the four questions every planning needs answered: how much do we really deliver, do we estimate honestly, who's overloaded, and are we on track today.

36avg velocity (SP) · last 6 sprints
+22% avgactual vs estimated effort
3/3failed sprints when committing 40+ SP
−6 SPbehind ideal burndown · Sprint 46, day 8
Velocity · committed vs completed
The gap is the overcommit habit — it opens every time the commitment passes 40.
Committed Completed
Estimation accuracy · by work type
Average estimated vs actual points, 34 stories over 6 sprints.
Estimated avg Actual avg
Workload · % allocation per sprint
Meetings + assigned points vs capacity. Over 100% two sprints in a row = red flag.
Sprint 46 burndown
52 SP committed · day 8 of 10 · 6 SP behind the ideal line — recoverable if nothing new enters
Ideal Actual
What the data says · AI insights